Upper Burrell Township moratorium
Upper Burrell Township, Pennsylvania paused new data center approvals for 6 months, citing specific project and infrastructure. The pause has ended. Checked 23 Nov 2026
The facts
- Applies to
- TECfusions' 'Keystone Connect' campus at the former Alcoa/Arconic Technical Center (up to 1,400 acres, potentially up to 3 GW); Building J is already operational and exempted from the moratorium, and a land-development plan for further work on that building was approved Aug. 5, 2026 despite the moratorium.
- Reason
- Public pressure over TECfusions' 'Keystone Connect' hyperscale data-center campus (up to 1,400 acres, potentially up to 3 gigawatts, at the former Alcoa/Arconic Technical Center); residents sought more transparency and regulation before further development.
- Term
- 180 days; does not apply to building permits already granted to TECfusions for work on its existing 'Building J' (already operational), and did not prevent the township from later approving a land development plan (Aug. 5, 2026) for further electrical/mechanical upgrades to that building. October 22 reporting gave a scheduled end of 2026-11-02; actual termination or extension is unverified.
- Legal basis
- Upper Burrell Township municipal curative amendment/moratorium on new data-center development (specific resolution number not located in sources reviewed)
- What happened next
- Upper Burrell Township Board of Supervisors adopted a 180-day moratorium/curative amendment on new data-center development (excluding already-permitted TECfusions work), to allow time to draft a data-center zoning ordinance; a land-use appeal challenging the township's handling of TECfusions' existing permits is pending in Westmoreland County court.
Campuses in reach
Cheswick Generating Station Data CenterAllegheny CountySite permit·≈37–170 MWCheswick/Springdale AI Data Center RedevelopmentAllegheny CountyZoning·Allegheny DC PropertyComcast Xsdc Data CenterAllegheny CountySite permit·≈4–20 MWContinental Broadband Pennsylvania LLC (Dba Expedient)Allegheny CountyAnnounced·≈3–16 MWPIT3 DataBank Center ExpansionAllegheny CountySite permit·≈23–110 MWTECfusions Keystone ConnectWestmoreland CountySite permit·3,000 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Upper Burrell Township votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.