EndedMoratorium

Upper Burrell Township moratorium

Upper Burrell Township, Pennsylvania paused new data center approvals for 6 months, citing specific project and infrastructure. The pause has ended. Checked 23 Nov 2026

The facts

Applies to
TECfusions' 'Keystone Connect' campus at the former Alcoa/Arconic Technical Center (up to 1,400 acres, potentially up to 3 GW); Building J is already operational and exempted from the moratorium, and a land-development plan for further work on that building was approved Aug. 5, 2026 despite the moratorium.
Reason
Public pressure over TECfusions' 'Keystone Connect' hyperscale data-center campus (up to 1,400 acres, potentially up to 3 gigawatts, at the former Alcoa/Arconic Technical Center); residents sought more transparency and regulation before further development.
Term
180 days; does not apply to building permits already granted to TECfusions for work on its existing 'Building J' (already operational), and did not prevent the township from later approving a land development plan (Aug. 5, 2026) for further electrical/mechanical upgrades to that building. October 22 reporting gave a scheduled end of 2026-11-02; actual termination or extension is unverified.
Legal basis
Upper Burrell Township municipal curative amendment/moratorium on new data-center development (specific resolution number not located in sources reviewed)
What happened next
Upper Burrell Township Board of Supervisors adopted a 180-day moratorium/curative amendment on new data-center development (excluding already-permitted TECfusions work), to allow time to draft a data-center zoning ordinance; a land-use appeal challenging the township's handling of TECfusions' existing permits is pending in Westmoreland County court.

Know when Upper Burrell Township votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Upper Burrell Township paused data centers?