Vienna Township moratorium

Vienna Township, Ohio paused new data center approvals on 17 Feb 2026 for 6 months, citing zoning and rules and infrastructure. Checked 23 Nov 2026

In force since 17 Feb 2026No end date on record

The facts

Applies to
None named.
Reason
Preemptive: allow zoning commission to draft data center regulations; followed Hubbard Township's moratorium.
Term
180 days originally; August 3 minutes record a 60-day extension to October 16, 2026. The Tribune Chronicle reported trustees approved another 180-day moratorium on October 26; its effective anchor, continuity and endpoint are unverified.
Legal basis
Trustee resolution (Vienna Township, Trumbull County) under R.C. 519, adapted from Hubbard Township's moratorium; extension resolution August 2026
What happened next
Zoning commission drafted data center regulations and sent them to the Trumbull County Planning Commission in August 2026. The Tribune Chronicle reported that on 2026-10-26 trustees voted 2–1 to return proposed zoning language to the commission and approved another 180-day moratorium; the adopted text and effective anchor remain unverified.

Know when Vienna Township votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Vienna Township paused data centers?