In forceMoratorium

Wabash County moratorium

Wabash County, Indiana paused new data center approvals on 31 Aug 2026, citing zoning and rules and land use. Checked 23 Nov 2026

In force since 31 Aug 2026No end date on record

The facts

Passed by
Wabash County Board of Commissioners, 31 Aug 2026
Reason
The county's 2022 Zoning Ordinance (Ordinance No. 2022-85-14) does not regulate data centers; the moratorium bars applications/permits for data center structures in all zoning districts of unincorporated Wabash County (and, upon local adoption, the towns of LaFontaine, Lagro, and Roann) while the Zoning Ordinance is amended
Term
Until a zoning amendment regulates data centers or eighteen calendar months from adoption, whichever occurs sooner. Section 3 makes county effectiveness upon adoption and effectiveness in LaFontaine, Lagro and Roann conditional on adoption by their legislative bodies.
Legal basis
Wabash County Board of Commissioners ordinance imposing a temporary moratorium on improvement-location permits for data center development, adopted 3-0 on 2026-08-31 following an Area Plan Commission favorable recommendation
What happened next
Board of Commissioners unanimously adopted a temporary moratorium on data center permits, following the Plan Commission's favorable recommendation

Know when Wabash County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Wabash County paused data centers?