Warren moratorium
Warren, Michigan paused new data center approvals on 25 Aug 2026, citing grid and power and zoning and rules. It covers 1 tracked campus. Checked 23 Nov 2026
In force since 25 Aug 2026No end date on record
The facts
- Passed by
- City Council, 25 Aug 2026
- Term
- 12 months
- What happened next
- City to define data centers and set zoning locations and conditions
- Applies to
- None; excludes existing facilities, approved uses, and accessory server rooms under 2,500 sq ft
- Reason
- Grid strain after July 2026 storms downed more than 60 power lines; zoning ordinance does not define data centers
- Legal basis
- City Council moratorium resolution prepared by council attorney Jeffrey Schroeder (Plunkett Cooney); number not located
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Warren votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.