Williams County, North Dakota paused new data center approvals on 20 Jun 2023, citing zoning and rules and water use. The pause has ended. It covers 1 tracked campus. Checked 23 Nov 2026
The facts
- Passed by
- Board of County Commissioners, 20 Jun 2023
- Applies to
- Specific project list and MW not identified in captured county records.
- Term
- 6 months, then extended to 2024-02-22
- Reason
- Existing code did not specifically regulate data centers; the permanent ordinance cites large water and electricity use, continuous sound, low-frequency noise, and off-site health impacts.
- Legal basis
- Board of County Commissioners moratorium action, per the county's own Planning & Zoning staff report accompanying the replacement ordinance: a 6-month moratorium on data center permits was instituted June 20, 2023, and extended by board vote on November 7, 2023 to run through February 22, 2024. The staff report describes both 2023 actions as board votes/motions and does not itself cite a resolution or motion number, and no separately numbered resolution for either action was found on williamsnd.civicweb.net or the county's current zoning page. Replaced by Ordinance 2024-01-02 (Planning & Zoning Commission recommended approval 8-0 on 2023-12-21), which amended Article 6 of the Williams County Zoning Ordinance and Subdivision Regulations to add Chapter 6-16, Data Centers.
- What happened next
- Chapter 6-16 of the Williams County Zoning Ordinance now allows data centers only by conditional use permit in Heavy Industrial and Agricultural districts, with a 1 mile setback from dwellings, schools, religious institutions, and parks, a 3 mile separation from other data centers, noise study requirements, power purchase agreement disclosure, financial security, road agreements, and reclamation requirements.
Campuses in reach
No tracked campus within 80 km
Know when Williams County votes
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.