Yadkin County moratorium
Yadkin County, North Carolina paused new data center approvals on 17 Aug 2026, citing water use and grid and power. Checked 23 Nov 2026
Started 17 Aug 20263 of 24 months passedEnds 17 Aug 2028
The facts
- What happened next
- Two-year moratorium adopted.
- Applies to
- WhiteFiber potential data center project in Yadkinville (inside town limits, not covered).
- Reason
- Concern over water use, energy demand, farmland and rural character; WhiteFiber announced a potential Yadkinville data center project
- Term
- Twenty-four months, from 2026-08-17 to 2028-08-17 or until a zoning text amendment addressing the covered uses, whichever comes first; applies in unincorporated county outside municipal extraterritorial jurisdictions.
- Legal basis
- Yadkin County data center moratorium ordinance, N.C.G.S. 160D-107 (ordinance number not located)
Campuses in reach
Compass Datacenters Statesville CampusIredell CountySite permit·CompassData center projectRowan CountyZoning·55 MWApple Inc.Catawba CountySite permit·≈62–290 MWBoyd Farms Data CenterCatawba CountySite permit·MicrosoftCLT40 Data CenterCatawba CountySite permit·≈7–33 MWLyle Creek Data CenterCatawba CountySite permit·Microsoft
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Yadkin County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.