City of Statesville moratorium
City of Statesville, North Carolina paused new data center approvals on 14 Sep 2026 for 6 months, citing zoning and rules and land use. It covers 1 tracked campus. Checked 23 Nov 2026
Started 14 Sep 20262 of 6 months passedEnds 13 Mar 2027
The facts
- Applies to
- Compass Datacenters Stamey Farm Road campus (approved Sept. 2025; exempt).
- Term
- 180 days from 2026-09-14 (to about 2027-03-13)
- What happened next
- 180-day moratorium adopted.
- Reason
- Rapid data center growth; residents opposed new facilities; does not affect the approved $1 billion Compass Datacenters campus on Stamey Farm Road
- Legal basis
- City of Statesville data center moratorium ordinance (number not located), N.C.G.S. 160D-107
Campuses in reach
Compass Datacenters Statesville CampusIredell CountySite permit·CompassApple Inc.Catawba CountySite permit·≈62–290 MWBoyd Farms Data CenterCatawba CountySite permit·MicrosoftCLT40 Data CenterCatawba CountySite permit·≈7–33 MWLyle Creek Data CenterCatawba CountySite permit·MicrosoftStover North Data CenterCatawba CountySite permit·Microsoft
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when City of Statesville votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.