In forceMoratorium

York Township moratorium

York Township, Michigan paused new data center approvals on 10 Mar 2026 for 6 months, citing specific project and zoning and rules. Checked 23 Nov 2026

Started 10 Mar 20268 of 12 months passedEnds 13 Mar 2027

The facts

Applies to
Potential 412-acre project tied to Sansone Group
What happened next
Consultant study and zoning work pending
Reason
Potential hyperscale proposal on Toyota-owned land and zoning-defensibility concerns
Term
180 days (Ordinance No. 167, effective 2026-03-18, expiring 2026-09-14); extended by Resolution #2026-19 for an additional 180 days (to approximately 2027-03-13) or until data center regulations are adopted, whichever occurs first
Legal basis
York Charter Township Ordinance No. 167, Data Center Moratorium Ordinance (first reading 2026-02-10, adopted 2026-03-10, effective 2026-03-18); extended by Resolution #2026-19 (adopted 2026-08-11, 6-0 roll call, Louis absent) under Section 4 of Ordinance No. 167

Know when York Township votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near York Township paused data centers?