Adc Plano

An estimated 24–110 MW data center campus in Plano, Texas, built by Aligned. It has had a site permit since October 2022 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Oct 2022
≈24–110 MWCapacity, our estimate
1Public records

How far along

  1. Announced
  2. Zoning
  3. Site permitOct 2022
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from October 2022. A building permit is the next step

Collin County, TexasParcel, substation and lines

The record

Owner
Aligned
Stage
Site permit
Capacity
≈24–110 MW
Public records
1
Latest record
25 Oct 2022
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Adc PlanoOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Adc Plano?
Aligned, according to public records.
How big is it?
About 24–110 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has had a site permit since October 2022.
Is there local opposition?
Not on record