A 72 MW data center campus in Sterling, Virginia, built by Aligned. It has had a site permit since February 2025 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Feb 2025
72 MWCapacity, as stated
1Public records
3Moratoria in force nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitFeb 2025
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from February 2025. A building permit is the next step. Loudoun County has a moratorium in force 3 km away

Loudoun County, VirginiaParcel, substation and lines

The record

Owner
Aligned
Stage
Site permit
Capacity
72 MW
Public records
1
Latest record
20 Feb 2025
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Aligned Data Centers IAD03Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Aligned Data Centers IAD03?
Aligned, according to public records.
How big is it?
72 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since February 2025.
Is there local opposition?
Yes. 3 moratoria in force nearby.