Alviso-Milpitas San Jose Campus
A data center campus in Santa Clara County, California, built by Microsoft. It has had a building permit since February 2026 and has 1 public record behind it. Checked 27 Nov 2026
Building permitStage since Feb 2026
Not on recordCapacity
1Public records
10Moratoria nearby
How far along
- Announced
- Zoning
- Site permit
- Building permitFeb 2026
- Construction
- Operating
The building permit dates from February 2026. Construction is the next step. Morgan Hill has a moratorium in force 11 km away
Santa Clara County, CaliforniaParcel, substation and lines
The record
- Owner
- Microsoft
- County
- Santa Clara County, CA
- Stage
- Building permit
- Capacity
- Not on record
- Public records
- 1
- Latest record
- 18 Feb 2026
- Opposition
- 9 moratoria in force and 1 ended nearby
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Utility, substation and 1 public record for Alviso-Milpitas San Jose CampusOpen the app, freeStart Pro · $299/mo
Opposition nearby
Morgan Hill moratorium11 kmIn forceGilroy moratorium26 kmIn forcePatterson moratorium57 kmIn forceHayward moratorium58 kmIn force
Opposition in CaliforniaKnow when this campus moves
Check your email to finish
Questions
Who owns Alviso-Milpitas San Jose Campus?
Microsoft, according to public records.
How big is it?
Not on record
Has it been approved?
Yes. It has had a building permit since February 2026.
Is there local opposition?
Yes. 9 moratoria in force and 1 ended nearby.