Vantage CA2 - Building 2
A 77 MW data center campus in Santa Clara, California, built by Vantage. It has had a site permit since August 2022 and has 13 public records behind it. Checked 27 Nov 2026
Site permitStage since Aug 2022
77 MWCapacity, as stated
13Public records
How far along
- Announced
- Zoning
- Site permitAug 2022
- Building permit
- Construction
- Operating
The site permit dates from August 2022. A building permit is the next step
Santa Clara County, CaliforniaParcel, substation and lines
The record
- Owner
- Vantage
- County
- Santa Clara County, CA
- Stage
- Site permit
- Capacity
- 77 MW
- Public records
- 13
- Latest record
- 8 Sep 2022
- Opposition
- None on record
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
13 records
- Record 1
- Record 2
- Record 3
Utility, substation and 13 public records for Vantage CA2 - Building 2Open the app, freeStart Pro · $299/mo
Nearby campuses
CoreSite Santa Clara (SV3)≈5 kmSite permit·CoresiteEdgeCore Silicon Valley SV01≈5 kmSite permit·EdgeCoreSJC Campus≈5 kmAnnounced·CloudHQMenlo Digital MD-SV1 (Sunnyvale)≈5 kmAnnounced·Menlo Equities
All campuses in Santa Clara CountyMore from Vantage
Vantage OH2 Millersport Campus696 MWSite permit·Millersport, OHVWPP Belmont Innovation (PCOR-2023-0016)≈240–1,100 MWZoning·Loudoun County, VAVantage Data Center - Doughlasville≈210–970 MWZoning·Douglas County, GAVantage Data Center AZ14≈120–570 MWSite permit·Unknown, AZ
All 71 campusesKnow when this campus moves
Check your email to finish
Questions
Who owns Vantage CA2 - Building 2?
Vantage, according to public records.
How big is it?
77 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since August 2022.
Is there local opposition?
Not on record