A 300 MW data center campus in Union City, Georgia, built by TA Realty. It has had a rezoning request on file since November 2024 and has 8 public records behind it. Checked 27 Nov 2026

ZoningStage since Nov 2024
300 MWCapacity, as stated
8Public records
10Moratoria nearby

How far along

  1. Announced
  2. ZoningNov 2024
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

The zoning dates from November 2024. Zoning approval is the next step. East Point (Fulton County) has a moratorium in force 13 km away

Fulton County, GeorgiaParcel, substation and lines

The record

Stage
Zoning
Capacity
300 MW
Public records
8
Latest record
12 Nov 2024
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
8 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 8 public records for ATL03/Red OakOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns ATL03/Red Oak?
TA Realty, according to public records.
How big is it?
300 MW, as stated in a public filing.
Has it been approved?
Not yet. It has had a rezoning request on file since November 2024.
Is there local opposition?
Yes. 9 moratoria in force and 1 ended nearby.