Cobb County moratorium
Cobb County, Georgia paused new data center approvals on 24 Feb 2026 for 6 months, citing infrastructure. It covers 9 tracked campuses. Checked 23 Nov 2026
Started 24 Feb 20269 of 12 months passedEnds 24 Feb 2027
The facts
- Passed by
- Board of Commissioners, 24 Feb 2026
- Applies to
- New permit applications in unincorporated Cobb County
- Reason
- Surge of metro Atlanta data centers and concern over infrastructure impacts
- Term
- Initial 180 days from 2026-02-24; extended another six months by resolution adopted 2026-08-11, expiring 2027-02-24.
- Legal basis
- Board of Commissioners moratorium resolution adopted unanimously 2026-02-24; extended by resolution adopted 2026-08-11 (BOC Regular Meeting agenda item 27, 'To adopt a resolution extending a temporary moratorium on rezoning applications and permits for new data centers in unincorporated Cobb County'). Resolution numbers not published in the portal or coverage reviewed.
- What happened next
- Moratorium extended 2026-08-11 through 2027-02-24; zoning code amendments for data centers being drafted.
Campuses in reach
Adp Data Center (DC1)Fulton CountySite permit·≈3–7 MWATL03/Red OakFulton CountyZoning·300 MWCCO06 Data CenterFulton CountySite permit·≈110–230 MWData Center Fulton, LLCFulton CountySite permit·40 MWEast Point Data CenterFulton CountyAnnounced·≈10–22 MWEdgeConneX ATL11-13Fulton CountyAnnounced·270 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Cobb County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (9 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.