Cardinal Energy Corporation

A 10 MW data center campus in Middletown, Virginia, built by Cardinal Energy. It has had a site permit since October 2025 and has 2 public records behind it. Checked 27 Nov 2026

Site permitStage since Oct 2025
10 MWCapacity, as stated
2Public records
1Moratorium in force nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitOct 2025
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from October 2025. A building permit is the next step. Front Royal has a moratorium in force 32 km away

Frederick County, VirginiaParcel, substation and lines

The record

Owner
Cardinal Energy
County
Frederick County, VA
Stage
Site permit
Capacity
10 MW
Public records
2
Latest record
2 Oct 2025
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for Cardinal Energy CorporationOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Cardinal Energy Corporation?
Cardinal Energy, according to public records.
How big is it?
10 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since October 2025.
Is there local opposition?
Yes. 1 moratorium in force nearby.