Adp Carmel Church Data Hub
Carmel Church Data Center
A 300 MW data center campus in Caroline, Virginia, built by Adp Carmel Church Data Hub. It has had a site permit since July 2024 and has 3 public records behind it. Checked 27 Nov 2026
Site permitStage since Jul 2024
300 MWCapacity, as stated
3Public records
How far along
- Announced
- Zoning
- Site permitJul 2024
- Building permit
- Construction
- Operating
The site permit dates from July 2024. A building permit is the next step
Caroline County, VirginiaParcel, substation and lines
The record
- Owner
- Adp Carmel Church Data Hub
- County
- Caroline County, VA
- Stage
- Site permit
- Capacity
- 300 MW
- Public records
- 3
- Latest record
- 16 Sep 2025
- Opposition
- None on record
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
3 records
- Record 1
- Record 2
- Record 3
Utility, substation and 3 public records for Carmel Church Data CenterOpen the app, freeStart Pro · $299/mo
Know when this campus moves
Check your email to finish
Questions
Who owns Carmel Church Data Center?
Adp Carmel Church Data Hub, according to public records.
How big is it?
300 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since July 2024.
Is there local opposition?
Not on record