CoreSite Santa Clara (SV3)

An estimated 20–94 MW data center campus in Santa Clara, California, built by Coresite. It has had a site permit since September 2022 and has 11 public records behind it. Checked 27 Nov 2026

Site permitStage since Sep 2022
≈20–94 MWCapacity, our estimate
11Public records
10Moratoria nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitSep 2022
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from September 2022. A building permit is the next step. Morgan Hill has a moratorium in force 11 km away

Santa Clara County, CaliforniaParcel, substation and lines

The record

Stage
Site permit
Capacity
≈20–94 MW
Public records
11
Latest record
8 Sep 2022
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
11 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 11 public records for CoreSite Santa Clara (SV3)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns CoreSite Santa Clara (SV3)?
Coresite, according to public records.
How big is it?
About 20–94 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has had a site permit since September 2022.
Is there local opposition?
Yes. 9 moratoria in force and 1 ended nearby.