data center building None

An estimated 35–160 MW data center campus in Loudoun County, Virginia, built by Microsoft. It has been under construction since September 2023 and has 1 public record behind it. Checked 27 Nov 2026

ConstructionStage since Sep 2023
≈35–160 MWCapacity, our estimate
1Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permit
  5. ConstructionSep 2023
  6. Operating

The construction dates from September 2023. Operating is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Stage
Construction
Capacity
≈35–160 MW
Public records
1
Latest record
14 Sep 2023
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for data center building NoneOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns data center building None?
Microsoft, according to public records.
How big is it?
About 35–160 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has been under construction since September 2023.
Is there local opposition?
Yes. 2 opposition records on file.