Data center project
An estimated 28–59 MW data center campus in Ashburn, Virginia, built by Amazon. It has had a site permit since September 2018 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since Sep 2018
≈28–59 MWCapacity, our estimate
1Public records
2Opposition records
How far along
- Announced
- Zoning
- Site permitSep 2018
- Building permit
- Construction
- Operating
The site permit dates from September 2018. A building permit is the next step
Loudoun County, VirginiaParcel, substation and lines
The record
- Owner
- Amazon
- County
- Loudoun County, VA
- Stage
- Site permit
- Capacity
- ≈28–59 MW
- Public records
- 1
- Latest record
- 13 Sep 2018
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Utility, substation and 1 public record for Data center projectOpen the app, freeStart Pro · $299/mo
Nearby campuses
INOVA Health System Phase 1 (EPLAN-2023-0051)≈5 kmSite permit·Beaumeade Crossing 11Copt Patriot Point, Phase 1A & 1B (STMP-2015-0008)≈5 kmSite permit·Bcore Copt DC 15NA Dulles Real Estate (STPL-2022-0012)≈5 kmSite permit·CorscaleAmazon Data Services, Inc. Iad 50 Iad 60 IAD-71 IAD-78 IAD-79 IAD-80≈5 kmSite permit·DC 8 9 10 De
All campuses in Loudoun CountyKnow when this campus moves
Check your email to finish
Questions
Who owns Data center project?
Amazon, according to public records.
How big is it?
About 28–59 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since September 2018.
Is there local opposition?
Yes. 2 opposition records on file.