Data center project

An estimated 43–91 MW data center campus in Haymarket, Virginia, built by Amazon. It has had a site permit since March 2015 and has 12 public records behind it. Checked 27 Nov 2026

Site permitStage since Mar 2015
≈43–91 MWCapacity, our estimate
12Public records

How far along

  1. Announced
  2. Zoning
  3. Site permitMar 2015
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from March 2015. A building permit is the next step

Prince William County, VirginiaParcel, substation and lines

The record

Owner
Amazon
Stage
Site permit
Capacity
≈43–91 MW
Public records
12
Latest record
31 Mar 2015
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
12 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 12 public records for Data center projectOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Data center project?
Amazon, according to public records.
How big is it?
About 43–91 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since March 2015.
Is there local opposition?
Not on record