Project Nova Southeast Site Plan (PLAT-2024-0185)

An estimated 210–960 MW data center campus in Ashburn, Virginia, built by SDC Ashburn Alpha I. It has had a site permit since October 2022 and has 2 public records behind it. Checked 27 Nov 2026

Site permitStage since Oct 2022
≈210–960 MWCapacity, our estimate
2Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permitOct 2022
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from October 2022. A building permit is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Stage
Site permit
Capacity
≈210–960 MW
Public records
2
Latest record
16 Jul 2024
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for Project Nova Southeast Site Plan (PLAT-2024-0185)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Project Nova Southeast Site Plan (PLAT-2024-0185)?
SDC Ashburn Alpha I, according to public records.
How big is it?
About 210–960 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has had a site permit since October 2022.
Is there local opposition?
Yes. 2 opposition records on file.