data center area (TLREZN2024-0003)

An estimated 100–470 MW data center campus in Leesburg, Virginia, built by Forestier Stiftung. It has had a rezoning request on file and has 1 public record behind it. Checked 27 Nov 2026

ZoningStage
≈100–470 MWCapacity, our estimate
1Public records
2Opposition records

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

A rezoning or land-use application is on file with the local jurisdiction. Zoning approval is the next step

Loudoun County, VirginiaParcel, substation and lines

The record

Owner
Forestier Stiftung
Stage
Zoning
Capacity
≈100–470 MW
Public records
1
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for data center area (TLREZN2024-0003)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns data center area (TLREZN2024-0003)?
Forestier Stiftung, according to public records.
How big is it?
About 100–470 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Not yet. It has had a rezoning request on file.
Is there local opposition?
Yes. 2 opposition records on file.