Amazon Data Services Inc - IAD-104/105/106

An estimated 65–140 MW data center campus in Manassas, Virginia, built by Amazon. It has had a site permit since March 2024 and has 5 public records behind it. Checked 27 Nov 2026

Site permitStage since Mar 2024
≈65–140 MWCapacity, our estimate
5Public records

How far along

  1. Announced
  2. Zoning
  3. Site permitMar 2024
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from March 2024. A building permit is the next step

Manassas City County, VirginiaParcel, substation and lines

The record

Owner
Amazon
Stage
Site permit
Capacity
≈65–140 MW
Public records
5
Latest record
28 Aug 2025
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
5 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 5 public records for Amazon Data Services Inc - IAD-104/105/106Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Amazon Data Services Inc - IAD-104/105/106?
Amazon, according to public records.
How big is it?
About 65–140 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since March 2024.
Is there local opposition?
Not on record