Microsoft Azure Gainesville Tech Park (REZ2020-00011)

An estimated 39–180 MW data center campus in Bristow, Virginia, built by Metromont. It has been under construction since June 2026 and has 10 public records behind it. Checked 27 Nov 2026

ConstructionStage since Jun 2026
≈39–180 MWCapacity, our estimate
10Public records

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permit
  5. ConstructionJun 2026
  6. Operating

The construction dates from June 2026. Operating is the next step

Prince William County, VirginiaParcel, substation and lines

The record

Stage
Construction
Capacity
≈39–180 MW
Public records
10
Latest record
25 Sep 2026
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
10 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 10 public records for Microsoft Azure Gainesville Tech Park (REZ2020-00011)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Microsoft Azure Gainesville Tech Park (REZ2020-00011)?
Metromont, with Microsoft also named, according to public records.
How big is it?
About 39–180 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has been under construction since June 2026.
Is there local opposition?
Not on record