Amazon Innovation Drive (PLN2007-00749)

An estimated 86–180 MW data center campus in Manassas Park, Virginia, built by Amazon. It was announced in September 2026 and has 2 public records behind it. Checked 27 Nov 2026

AnnouncedStage since Sep 2026
≈86–180 MWCapacity, our estimate
2Public records

How far along

  1. AnnouncedSep 2026
  2. Zoning
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

The announced dates from September 2026. A rezoning or site permit is the next step

The record

Owner
Amazon
County
Manassas Park County, VA
Stage
Announced
Capacity
≈86–180 MW
Public records
2
Latest record
20 Oct 2026
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for Amazon Innovation Drive (PLN2007-00749)Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Amazon Innovation Drive (PLN2007-00749)?
Amazon, according to public records.
How big is it?
About 86–180 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Not yet. It was announced in September 2026.
Is there local opposition?
Not on record