Amazon Data Services Inc - IAD-134/135/136

An estimated 51–110 MW data center campus in Chantilly, Virginia, built by Amazon. It has had a site permit since January 2023 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Jan 2023
≈51–110 MWCapacity, our estimate
1Public records

How far along

  1. Announced
  2. Zoning
  3. Site permitJan 2023
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from January 2023. A building permit is the next step

Fairfax County, VirginiaParcel, substation and lines

The record

Owner
Amazon
Stage
Site permit
Capacity
≈51–110 MW
Public records
1
Latest record
12 Jan 2023
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Amazon Data Services Inc - IAD-134/135/136Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Amazon Data Services Inc - IAD-134/135/136?
Amazon, according to public records.
How big is it?
About 51–110 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since January 2023.
Is there local opposition?
Not on record