Mci Data Center (SPAM-2005-0055)
An estimated 200–430 MW data center campus in Ashburn, Virginia, built by Digital Realty. It has had a site permit since May 2005 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since May 2005
≈200–430 MWCapacity, our estimate
1Public records
2Opposition records
How far along
- Announced
- Zoning
- Site permitMay 2005
- Building permit
- Construction
- Operating
The site permit dates from May 2005. A building permit is the next step
Loudoun County, VirginiaParcel, substation and lines
The record
- Owner
- Digital Realty
- County
- Loudoun County, VA
- Stage
- Site permit
- Capacity
- ≈200–430 MW
- Public records
- 1
- Latest record
- 25 May 2005
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Utility, substation and 1 public record for Mci Data Center (SPAM-2005-0055)Open the app, freeStart Pro · $299/mo
Nearby campuses
Zebra VWP permit (PCOR-2023-0015)≈5 kmZoning·Darab Ventures ThreeData center project≈5 kmZoning·Quantum ParkQuantum Connect Ashburn≈5 kmSite permit·PowerHouseDigital Loudoun III (SPAM-2016-0109)≈5 kmSite permit·Digital Realty
All campuses in Loudoun CountyMore from Digital Realty
Digital Realty Stilesboro campus1,300 MWZoning·Cartersville, GADigital Dulles Land Condo (EPLAN-2024-0060)1,000 MWSite permit·Loudoun County, VADigital Realty Fort Gillem Campus (ATL15/16)200 MWSite permit·Forest Park, GAData center project160 MWAnnounced·Garland, TX
All 68 campusesKnow when this campus moves
Check your email to finish
Questions
Who owns Mci Data Center (SPAM-2005-0055)?
Digital Realty, according to public records.
How big is it?
About 200–430 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since May 2005.
Is there local opposition?
Yes. 2 opposition records on file.