East Point Data Center

An estimated 10–22 MW data center campus in Alpharetta, Georgia, built by Lincoln Property. It has been announced and has 9 public records behind it. Checked 27 Nov 2026

AnnouncedStage
≈10–22 MWCapacity, our estimate
9Public records
7Moratoria nearby

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

Publicly announced by the developer, a utility or local officials, with no land-use filing found yet. A rezoning or site permit is the next step. East Point (Fulton County) has a moratorium in force 13 km away

Fulton County, GeorgiaParcel, substation and lines

The record

Stage
Announced
Capacity
≈10–22 MW
Public records
9
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
9 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 9 public records for East Point Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns East Point Data Center?
Lincoln Property, with Lincoln Rackhouse and Microsoft also named, according to public records.
How big is it?
About 10–22 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Not yet. It has been announced.
Is there local opposition?
Yes. 6 moratoria in force and 1 ended nearby.