EdgeConneX Chicago - EDCCHI01
A 20 MW data center campus in Elk Grove, Illinois, built by EdgeConneX. It has had a building permit since April 2026 and has 7 public records behind it. Checked 27 Nov 2026
Building permitStage since Apr 2026
20 MWCapacity, as stated
7Public records
2Opposition records
How far along
- Announced
- Zoning
- Site permit
- Building permitApr 2026
- Construction
- Operating
The building permit dates from April 2026. Construction is the next step
Cook County, IllinoisParcel, substation and lines
The record
- Owner
- EdgeConneX
- County
- Cook County, IL
- Stage
- Building permit
- Capacity
- 20 MW
- Public records
- 7
- Latest record
- 16 Apr 2026
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
7 records
- Record 1
- Record 2
- Record 3
Utility, substation and 7 public records for EdgeConneX Chicago - EDCCHI01Open the app, freeStart Pro · $299/mo
Know when this campus moves
Check your email to finish
Questions
Who owns EdgeConneX Chicago - EDCCHI01?
EdgeConneX, according to public records.
How big is it?
20 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a building permit since April 2026.
Is there local opposition?
Yes. 2 opposition records on file.