Gccisd New Technology Data Center

An estimated 7–31 MW data center campus in Baytown, Texas, built by Durotech. It has had a site permit since June 2018 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Jun 2018
≈7–31 MWCapacity, our estimate
1Public records
1Moratorium in force nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitJun 2018
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from June 2018. A building permit is the next step. Austin County has a moratorium in force 82 km away

Harris County, TexasParcel, substation and lines

The record

Owner
Durotech
Stage
Site permit
Capacity
≈7–31 MW
Public records
1
Latest record
1 Jun 2018
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Gccisd New Technology Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Gccisd New Technology Data Center?
Durotech, according to public records.
How big is it?
About 7–31 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Yes. It has had a site permit since June 2018.
Is there local opposition?
Yes. 1 moratorium in force nearby.