Hockley Data Center

A 410 MW data center campus in Houston, Texas, built by SF Houh. It has had a site permit since May 2024 and has 5 public records behind it. Checked 27 Nov 2026

Site permitStage since May 2024
410 MWCapacity, as stated
5Public records
1Moratorium in force nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitMay 2024
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from May 2024. A building permit is the next step. Austin County has a moratorium in force 82 km away

Harris County, TexasParcel, substation and lines

The record

Owner
SF Houh
Stage
Site permit
Capacity
410 MW
Public records
5
Latest record
29 Aug 2024
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
5 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 5 public records for Hockley Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Hockley Data Center?
SF Houh, according to public records.
How big is it?
410 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since May 2024.
Is there local opposition?
Yes. 1 moratorium in force nearby.