Hillsboro 3 Data Center
A 36 MW data center campus in Hillsboro, Oregon, built by QTS. It has had a site permit since January 2021 and has 5 public records behind it. Checked 27 Nov 2026
Site permitStage since Jan 2021
36 MWCapacity, as stated
5Public records
19Moratoria nearby
How far along
- Announced
- Zoning
- Site permitJan 2021
- Building permit
- Construction
- Operating
The site permit dates from January 2021. A building permit is the next step. Woodburn has a moratorium in force 49 km away
Washington County, OregonParcel, substation and lines
The record
- Owner
- QTS
- County
- Washington County, OR
- Stage
- Site permit
- Capacity
- 36 MW
- Public records
- 5
- Latest record
- 28 Mar 2022
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
5 records
- Record 1
- Record 2
- Record 3
Utility, substation and 5 public records for Hillsboro 3 Data CenterOpen the app, freeStart Pro · $299/mo
Opposition nearby
City of Hillsboro moratorium9 kmEndedWoodburn moratorium49 kmIn forceSalem moratorium69 kmIn forceClackamas County moratorium81 kmIn force
Opposition in OregonKnow when this campus moves
Check your email to finish
Questions
Who owns Hillsboro 3 Data Center?
QTS, according to public records.
How big is it?
36 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since January 2021.
Is there local opposition?
Yes. 16 moratoria in force and 2 pending and 1 ended nearby.