Woodburn moratorium
Woodburn, Oregon paused new data center approvals on 14 Sep 2026 for 4 months, citing specific project and zoning and rules. Checked 23 Nov 2026
Started 14 Sep 20262 of 4 months passedEnds 12 Jan 2027
The facts
- Passed by
- Woodburn City Council, 14 Sep 2026
- Reason
- specific_project
- Applies to
- No formal application received; city staff learned that data center developer Verrus was exploring a site 'in or near Woodburn,' including the 237-acre Southwest Industrial Reserve Area.
- Term
- 120 days from adoption (2026-09-14 to 2027-01-12); the City Manager stated the council could extend it to up to six months total.
- Legal basis
- Resolution No. 2267, adopted by Woodburn City Council on September 14, 2026 under ORS 197.505–540. The city filed a 45-day notice with the Oregon Department of Land Conservation and Development.
- What happened next
- City Council unanimously adopted a 120-day moratorium on considering new data center applications while the city reviews and potentially revises its development code.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Woodburn votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.