Irea Highfield Data Center SSS4275

A 23 MW data center campus in Parker, Colorado, built by Flexential. It has had a site permit since December 2017 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Dec 2017
23 MWCapacity, as stated
1Public records
11Moratoria in force nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitDec 2017
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from December 2017. A building permit is the next step. Monument has a moratorium in force 26 km away

Douglas County, ColoradoParcel, substation and lines

The record

Stage
Site permit
Capacity
23 MW
Public records
1
Latest record
6 Dec 2017
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Irea Highfield Data Center SSS4275Open the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Irea Highfield Data Center SSS4275?
Flexential, with Intermountain Rural Electric Association also named, according to public records.
How big is it?
23 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since December 2017.
Is there local opposition?
Yes. 11 moratoria in force nearby.