Monument moratorium
Monument, Colorado paused new data center approvals on 20 Jul 2026, citing zoning and rules. Checked 23 Nov 2026
In force since 20 Jul 2026No end date on record
The facts
- Reason
- No data center proposal was pending; staff planned to address data centers in a broader rewrite of the land-development code.
- Term
- Six months from the ordinance effective date, unless extended by Town Council following a public hearing (section2). Section9 makes effectiveness ten days after final publication; section7 requires full-text website publication for at least ten days. Actual final publication date and therefore the precise effective/end dates remain unverified.
- Legal basis
- Town of Monument Ordinance18-2026. The recovered six-page Municode-linked PDF contains an unsigned copy on pages1-3 and a signed/sealed copy on pages4-6. Page6 records adoption July20,2026 by6for/0against, with MayorProTem SteveKing and TownClerk TinaErickson signatures. Section8 states that failure to authenticate does not invalidate or suspend operation; actual publication and later Council action remain separate questions.
Campuses in reach
ComparkDouglas CountySite permit·23 MWEdgeConneX, Inc - Denver CampusDouglas CountySite permit·≈14–66 MWFlexential ParkerDouglas CountyConstruction·23 MWIrea Highfield Data Center SSS4275Douglas CountySite permit·23 MWFontus Data Centre ProjectTeller CountyAnnounced·380 MWNovva Colorado - Data Center CO SpringsEl Paso CountySite permit·30 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Monument votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.