Oracle America
A data center campus in Broomfield, Colorado, built by Oracle. It has had a site permit since October 2015 and has 2 public records behind it. Checked 27 Nov 2026
Site permitStage since Oct 2015
Not on recordCapacity
2Public records
20Moratoria nearby
How far along
- Announced
- Zoning
- Site permitOct 2015
- Building permit
- Construction
- Operating
The site permit dates from October 2015. A building permit is the next step. Broomfield has a moratorium in force 2 km away
Broomfield County, ColoradoParcel, substation and lines
The record
Opposition nearby
Broomfield moratorium2 kmIn forceArvada moratorium17 kmIn forceCommerce City moratorium19 kmIn forceBrighton moratorium22 kmIn force
Opposition in ColoradoKnow when this campus moves
Check your email to finish
Questions
Who owns Oracle America?
Oracle, according to public records.
How big is it?
Not on record
Has it been approved?
Yes. It has had a site permit since October 2015.
Is there local opposition?
Yes. 19 moratoria in force and 1 pending nearby.