Oracle America Inc
An estimated 88–410 MW data center campus in Malvern, Pennsylvania, built by Oracle. It was announced in October 2017 and has 1 public record behind it. Checked 27 Nov 2026
AnnouncedStage since Oct 2017
≈88–410 MWCapacity, our estimate
1Public records
3Moratoria nearby
How far along
- AnnouncedOct 2017
- Zoning
- Site permit
- Building permit
- Construction
- Operating
The announced dates from October 2017. A rezoning or site permit is the next step. West Whiteland Township has a moratorium in force 12 km away
Chester County, PennsylvaniaParcel, substation and lines
The record
- Owner
- Oracle
- County
- Chester County, PA
- Stage
- Announced
- Capacity
- ≈88–410 MW
- Public records
- 1
- Latest record
- 27 Oct 2017
- Opposition
- 2 moratoria in force and 1 ended nearby
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Opposition nearby
West Whiteland Township moratorium12 kmIn forceEast Whiteland Township moratorium19 kmEndedLittle Britain Township moratorium36 kmIn force
Opposition in PennsylvaniaKnow when this campus moves
Check your email to finish
Questions
Who owns Oracle America Inc?
Oracle, according to public records.
How big is it?
About 88–410 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Not yet. It was announced in October 2017.
Is there local opposition?
Yes. 2 moratoria in force and 1 ended nearby.