An estimated 4–8 MW data center campus in Washington Dulles International Airport, Virginia, built by QTS. It has had a site permit since March 2015 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since Mar 2015
≈4–8 MWCapacity, our estimate
1Public records
2Opposition records
How far along
- Announced
- Zoning
- Site permitMar 2015
- Building permit
- Construction
- Operating
The site permit dates from March 2015. A building permit is the next step
Loudoun County, VirginiaParcel, substation and lines
The record
- Owner
- QTS
- County
- Loudoun County, VA
- Stage
- Site permit
- Capacity
- ≈4–8 MW
- Public records
- 1
- Latest record
- 31 Mar 2015
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Know when this campus moves
Check your email to finish
Questions
Who owns QTS Dulles, LLC?
QTS, according to public records.
How big is it?
About 4–8 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since March 2015.
Is there local opposition?
Yes. 2 opposition records on file.