Sat 40 Data Center
An estimated 48–220 MW data center campus in San Antonio, Texas, built by Microsoft. It has had a site permit since March 2024 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since Mar 2024
≈48–220 MWCapacity, our estimate
1Public records
How far along
- Announced
- Zoning
- Site permitMar 2024
- Building permit
- Construction
- Operating
The site permit dates from March 2024. A building permit is the next step
Bexar County, TexasParcel, substation and lines
The record
- Owner
- Microsoft
- County
- Bexar County, TX
- Stage
- Site permit
- Capacity
- ≈48–220 MW
- Public records
- 1
- Latest record
- 1 Mar 2024
- Opposition
- None on record
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Know when this campus moves
Check your email to finish
Questions
Who owns Sat 40 Data Center?
Microsoft, according to public records.
How big is it?
About 48–220 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has had a site permit since March 2024.
Is there local opposition?
Not on record