Vantage TX 11
A 32 MW data center campus in San Antonio, Texas, built by Vantage. It has had a site permit since November 2023 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since Nov 2023
32 MWCapacity, as stated
1Public records
How far along
- Announced
- Zoning
- Site permitNov 2023
- Building permit
- Construction
- Operating
The site permit dates from November 2023. A building permit is the next step
Bexar County, TexasParcel, substation and lines
The record
- Owner
- Vantage
- County
- Bexar County, TX
- Stage
- Site permit
- Capacity
- 32 MW
- Public records
- 1
- Latest record
- 28 Nov 2023
- Opposition
- None on record
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Nearby campuses
SAT Campus≈5 kmAnnounced·CloudHQSat 40 Data Center≈5 kmSite permit·MicrosoftMicrosoft≈10 kmSite permit·MicrosoftSpecial Proj - SAT14 Data Cent Shell - Bldgs 1-3≈10 kmSite permit·Microsoft
All campuses in Bexar CountyMore from Vantage
Vantage OH2 Millersport Campus696 MWSite permit·Millersport, OHVWPP Belmont Innovation (PCOR-2023-0016)≈240–1,100 MWZoning·Loudoun County, VAVantage Data Center - Doughlasville≈210–970 MWZoning·Douglas County, GAVantage Data Center AZ14≈120–570 MWSite permit·Unknown, AZ
All 71 campusesKnow when this campus moves
Check your email to finish
Questions
Who owns Vantage TX 11?
Vantage, according to public records.
How big is it?
32 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since November 2023.
Is there local opposition?
Not on record