UHG - Chaska

An estimated 61–280 MW data center campus in Chaska, Minnesota, built by United Health Group. It has had a site permit and has 2 public records behind it. Checked 27 Nov 2026

Site permitStage
≈61–280 MWCapacity, our estimate
2Public records
2Moratoria in force nearby

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

A site plan, grading, air or other site permit has been filed or issued. A building permit is the next step. Carver has a moratorium in force 2 km away

Carver County, MinnesotaParcel, substation and lines

The record

Owner
United Health Group
Stage
Site permit
Capacity
≈61–280 MW
Public records
2
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for UHG - ChaskaOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns UHG - Chaska?
United Health Group, according to public records.
How big is it?
About 61–280 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has had a site permit.
Is there local opposition?
Yes. 2 moratoria in force nearby.