Zayo Group, LLC
An estimated 16–34 MW data center campus in Ashburn, Virginia, built by Zayo Group. It has had a site permit since August 2025 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since Aug 2025
≈16–34 MWCapacity, our estimate
1Public records
2Opposition records
How far along
- Announced
- Zoning
- Site permitAug 2025
- Building permit
- Construction
- Operating
The site permit dates from August 2025. A building permit is the next step
Loudoun County, VirginiaParcel, substation and lines
The record
- Owner
- Zayo Group
- County
- Loudoun County, VA
- Stage
- Site permit
- Capacity
- ≈16–34 MW
- Public records
- 1
- Latest record
- 4 Aug 2025
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Nearby campuses
Ashburn Technology Park S 2 (SPAM-2006-0128)≈5 kmSite permit·Loudoun Corporate Center 2Intergate Ashburn Data Center (ESMT-2012-0040)≈5 kmSite permit·SabeyAmazon Data Services IAD-215≈5 kmSite permit·AmazonAshburn Technology Park Sec 3 (PARC-2017-0004)≈5 kmZoning·Loudoun Corp Center Section 3
All campuses in Loudoun CountyKnow when this campus moves
Check your email to finish
Questions
Who owns Zayo Group, LLC?
Zayo Group, according to public records.
How big is it?
About 16–34 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since August 2025.
Is there local opposition?
Yes. 2 opposition records on file.