Zayo Group, LLC

An estimated 2–5 MW data center campus in Tysons, Virginia, built by Zayo Group. It has had a site permit since January 2009 and has 2 public records behind it. Checked 27 Nov 2026

Site permitStage since Jan 2009
≈2–5 MWCapacity, our estimate
2Public records

How far along

  1. Announced
  2. Zoning
  3. Site permitJan 2009
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from January 2009. A building permit is the next step

Fairfax County, VirginiaParcel, substation and lines

The record

Stage
Site permit
Capacity
≈2–5 MW
Public records
2
Latest record
29 May 2019
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for Zayo Group, LLCOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Zayo Group, LLC?
Zayo Group, according to public records.
How big is it?
About 2–5 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a site permit since January 2009.
Is there local opposition?
Not on record