Abilene
Abilene is market 29 of 34: about 387 MW across 1 campus in 4 counties. 0 under construction and 0 moratoria in force. Checked 28 Nov 2026
The shape of the market
By stage
- Site permit1
Stated and estimated
- Stated on record297 MW
- Our estimate≈90 MW
Who is building
- Lancium AbileneNot on record1
By county
- Taylor1
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Abilene in the app, free
Questions
How many data centers are in Abilene?
3 tracked pipeline campuses (387 MW estimated total, 297 MW reported) across 4 counties in Texas. Key signals: 3 pipeline sites in high/extremely high water stress.
Estimated pipeline MW combines reported capacity (297 MW) with estimates from floor area, acreage, investment or backup generation. 0.0% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
No moratorium is in force in Abilene today. 1 moratorium and 0 petitions are on record across the market. 3 of 3 campuses sit in high water stress.
How is this market drawn?
Abilene is the 4 counties around its campuses in Texas, in ERCOT. It ranks 29 of 34 markets by estimated pipeline.
How large is the Abilene data center pipeline?
Wattlas tracks 3 upcoming pipeline campuses in Abilene (2 verified, 0 under construction, 3 permitted), representing 297 MW in reported capacity and 387 MW total estimated pipeline. Projects with the largest reported figures include Core Scientific Denton Data Center Campus (50–499 MW).
What are industrial power rates and serving utilities in Abilene?
Abilene sits in ERCOT. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Abilene data centers?
Across tracked campuses in Abilene, Wattlas links 0 active or extended moratoria (1 total) and 0 public petitions. On physical site risk, 3 of 3 pipeline campuses sit in High or Extremely High baseline water stress (0 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Abilene data center sites show active satellite land clearing?
Of 2 pinpointed pipeline sites monitored with satellite imagery in Abilene, 0 (0.0%) show active earthwork or pad expansion, including 0 sites clearing ahead of a reported construction stage.