Austin / San Antonio
Austin / San Antonio is market 11 of 34: about 6.5 GW across 24 campuses in 11 counties. 2 under construction and 1 moratorium in force. Checked 28 Nov 2026
Largest campuses
All 24 campuses
The shape of the market
By stage
- Announced5
- Site permit16
- Building permit1
- Construction2
Stated and estimated
- Stated on record695 MW
- Our estimate≈5.8 GW
Who is building
MicrosoftNot on record5
TractNot on record2- Hays City1,200 MW1
- MDC Building 11,200 MW1
- Mine Service1,200 MW1
By county
- Bexar9
- Medina4
- Williamson4
- Travis3
- Caldwell1
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Austin / San Antonio in the app, free
Questions
How many data centers are in Austin / San Antonio?
28 tracked pipeline campuses (6.5 GW estimated total, 695 MW reported) across 11 counties in Texas. Key signals: 5 sites showing earthwork in satellite imagery, 1 active/extended moratorium, 17 pipeline sites in high/extremely high water stress.
Estimated pipeline MW combines reported capacity (695 MW) with estimates from floor area, acreage, investment or backup generation. 25.0% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
1 moratorium is in force in Austin / San Antonio, covering 1 campus. 1 moratorium and 12 petitions are on record across the market. 17 of 28 campuses sit in high water stress.
How is this market drawn?
Austin / San Antonio is the 11 counties around its campuses in Texas, in ERCOT. It ranks 11 of 34 markets by estimated pipeline.
How large is the Austin / San Antonio data center pipeline?
Wattlas tracks 28 upcoming pipeline campuses in Austin / San Antonio (11 verified, 2 under construction, 19 permitted), representing 695 MW in reported capacity and 6,463 MW total estimated pipeline. Projects with the largest reported figures include Stargate Milam County (Orion) (1,000+ MW), Taylor Technology Campus (1,000+ MW), Tract Applewhite (500–999 MW).
What are industrial power rates and serving utilities in Austin / San Antonio?
Austin / San Antonio sits in ERCOT. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Austin / San Antonio data centers?
Across tracked campuses in Austin / San Antonio, Wattlas links 1 active or extended moratorium (1 total) and 12 public petitions. On physical site risk, 17 of 28 pipeline campuses sit in High or Extremely High baseline water stress (5 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Austin / San Antonio data center sites show active satellite land clearing?
Of 20 pinpointed pipeline sites monitored with satellite imagery in Austin / San Antonio, 5 (25.0%) show active earthwork or pad expansion, including 5 sites clearing ahead of a reported construction stage.