Central & East Mississippi

Central & East Mississippi is market 24 of 34: about 632 MW across 3 campuses in 7 counties. 1 under construction and 1 moratorium in force. Checked 28 Nov 2026

3Campuses
≈632 MWIn the pipeline
1Under construction
1Moratoria in force

The shape of the market

By stage

  • Site permit2
  • Construction1

Stated and estimated

  • Stated on recordNot on record
  • Our estimate≈632 MW

Who is building

By county

  • Rankin2
  • Hinds1
Power in this market
  • Utilities serving these campuses
  • Grid requests on file
  • Substations, water stress and flood
  • Download this market as CSV
Power, water and flood for Central & East MississippiOpen the app, freeStart Pro · $299/mo

Track Central & East Mississippi in the app, free

Check your email to finish

Questions

How many data centers are in Central & East Mississippi?

4 tracked pipeline campuses (632 MW estimated total, 0 MW reported) across 7 counties in Mississippi. Key signals: 1 site showing earthwork in satellite imagery, 1 active/extended moratorium.

Estimated pipeline MW combines reported capacity (0 MW) with estimates from floor area, acreage, investment or backup generation. 50.0% of monitored sites show clearing.

Who is building the most?
Which counties have paused new data centers?

1 moratorium is in force in Central & East Mississippi, covering 1 campus. 1 moratorium and 0 petitions are on record across the market. 0 of 4 campuses sit in high water stress.

How is this market drawn?

Central & East Mississippi is the 7 counties around its campuses in Mississippi, in MISO. It ranks 24 of 34 markets by estimated pipeline.

How large is the Central & East Mississippi data center pipeline?

Wattlas tracks 4 upcoming pipeline campuses in Central & East Mississippi (1 verified, 1 under construction, 2 permitted), representing 0 MW in reported capacity and 632 MW total estimated pipeline. Projects with the largest reported figures include Taurus Data Center Hub (50–499 MW), Adp Rankin Data Hub, LLC, Data Center (50–499 MW).

What are industrial power rates and serving utilities in Central & East Mississippi?

Central & East Mississippi sits in MISO. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.

What local opposition, moratoria, or water risks affect Central & East Mississippi data centers?

Across tracked campuses in Central & East Mississippi, Wattlas links 1 active or extended moratorium (1 total) and 0 public petitions. On physical site risk, 0 of 4 pipeline campuses sit in High or Extremely High baseline water stress (0 Extremely High). Floodplain and ozone screening are included in Wattlas access.

How many Central & East Mississippi data center sites show active satellite land clearing?

Of 2 pinpointed pipeline sites monitored with satellite imagery in Central & East Mississippi, 1 (50.0%) show active earthwork or pad expansion, including 1 site clearing ahead of a reported construction stage.