Memphis / Mid-South
Memphis / Mid-South is market 33 of 34: about 70 MW across 3 campuses in 7 counties. 0 under construction and 1 moratorium in force. Checked 28 Nov 2026
The shape of the market
By stage
- Site permit3
Stated and estimated
- Stated on recordNot on record
- Our estimate≈70 MW
Who is building
5C Data Centers60 MW1
Oppidan10 MW1- FoxmanNot on record1
By county
- Shelby, TN2
- Montgomery, TN1
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Memphis / Mid-South in the app, free
Questions
How many data centers are in Memphis / Mid-South?
3 tracked pipeline campuses (70 MW estimated total, 0 MW reported) across 7 counties in Tennessee & Mississippi. Key signals: 1 site showing earthwork in satellite imagery, 1 active/extended moratorium, 1 pipeline site in high/extremely high water stress.
Estimated pipeline MW combines reported capacity (0 MW) with estimates from floor area, acreage, investment or backup generation. 33.3% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
1 moratorium is in force in Memphis / Mid-South, covering 2 campuses. 1 moratorium and 0 petitions are on record across the market. 1 of 3 campuses sit in high water stress.
How is this market drawn?
Memphis / Mid-South is the 7 counties around its campuses in Tennessee & Mississippi, in Non-ISO. It ranks 33 of 34 markets by estimated pipeline.
How large is the Memphis / Mid-South data center pipeline?
Wattlas tracks 3 upcoming pipeline campuses in Memphis / Mid-South (2 verified, 0 under construction, 3 permitted), representing 0 MW in reported capacity and 70 MW total estimated pipeline. Projects with the largest reported figures include 5C MEM01 Inc (50–499 MW), Oppidan Data Center (Under 50 MW).
What are industrial power rates and serving utilities in Memphis / Mid-South?
Memphis / Mid-South sits in Non-ISO. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Memphis / Mid-South data centers?
Across tracked campuses in Memphis / Mid-South, Wattlas links 1 active or extended moratorium (1 total) and 0 public petitions. On physical site risk, 1 of 3 pipeline campuses sit in High or Extremely High baseline water stress (0 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Memphis / Mid-South data center sites show active satellite land clearing?
Of 3 pinpointed pipeline sites monitored with satellite imagery in Memphis / Mid-South, 1 (33.3%) show active earthwork or pad expansion, including 1 site clearing ahead of a reported construction stage.