Charlotte moratorium

Charlotte, North Carolina paused new data center approvals on 8 Jun 2026, citing specific project and property values. It covers 27 tracked campuses. Checked 23 Nov 2026

Started 8 Jun 20266 of 16 months passedEnds 18 Oct 2027

The facts

Applies to
Proposed American Towers data center, east Charlotte
Reason
Public concern over electricity rates, water consumption, noise, and neighborhood impacts tied to a proposed American Towers data center in east Charlotte; a May 26, 2026 public hearing drew 50-plus speakers
Term
Initially 150 days through November 5, 2026; extension commences November 6, 2026 and ends no later than October 18, 2027, or upon earlier adoption of applicable standards and policies.
Legal basis
Ordinance Imposing a Temporary Moratorium on Acceptance, Processing, and Approval of Applications for New Telecommunications and Data Storage Facilities within the City of Charlotte and its ETJ pursuant to N.C.G.S. 160D-107, adopted 2026-06-08 after a 2026-05-26 legislative hearing; ordinance-book number not shown on the posted copy
What happened next
150-day moratorium on new data-center development/rezoning petitions to allow time for policy development

Know when Charlotte votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (27 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Charlotte paused data centers?