In forceMoratorium

City of Kings Mountain moratorium

City of Kings Mountain, North Carolina paused new data center approvals on 24 Feb 2026 for 6 months, citing zoning and rules and infrastructure. It covers 3 tracked campuses. Checked 23 Nov 2026

Started 24 Feb 20269 of 18 months passedEnds 25 Aug 2027

The facts

Applies to
No named project in captured agenda packet.
Reason
Numerous inquiries from developers; UDO written in 2021 did not define data centers or set standards for location, buffering, lighting, noise, utility usage, or on-site generation.
Term
Originally 182 days (2026-02-24 to 2026-08-25); extended on 2026-08-25 for an additional twelve months, to about 2027-08-25, unless ended earlier by council
Legal basis
Ordinance 26-11, adopted 5-2 on motion by Councilmember Annie Thombs (seconded by Lemmond), enacting 182-day moratorium on permitting new data centers; N.C.G.S. 160D-107(d) findings (problems/conditions, scope, duration, schedule) read into the record by Planning Director Henry Earle (per Feb. 24, 2026 minutes). Dissenting: Neisler, Fletcher. Extended 2026-08-25 by a further ordinance 'to extend the existing moratorium on permitting new data centers for an additional twelve months' (agenda item 10D), adopted 6-1 (Neisler dissenting); extension ordinance number not published in materials located.
What happened next
Extended 12 months on 2026-08-25; UDO text amendments for data centers still in preparation with the Planning and Zoning Board.

Know when City of Kings Mountain votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (3 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near City of Kings Mountain paused data centers?