City of East Wenatchee moratorium
City of East Wenatchee, Washington paused new data center approvals on 27 Mar 2018, citing zoning and rules and infrastructure. The pause has ended. It covers 14 tracked campuses. Checked 23 Nov 2026
Started 27 Mar 2018Ended
The facts
- Applies to
- Not identified in captured city ordinance records; regional reports note moratoria coincided with redirected bitcoin investment in the Wenatchee Valley
- Reason
- Rapid cryptocurrency mining growth, high continuous electric demand, fire/life-safety risk, and Douglas County PUD electric infrastructure planning concerns identified in Ordinance 2018-21 recitals
- Term
- Initial six-month interim control (Ord. 2018-06: 2018-03-27 to 2018-09-27, per recital 2.10 of Ord. 2018-21); twelve-month extension under Ordinance 2018-21
- Legal basis
- Ordinance 2018-06; Ordinance 2018-21 (twelve-month interim official zoning controls under RCW 35A.63.220 and RCW 36.70A.390); permanent regulations adopted by Ordinance 2019-19, which added EWMC 17.08.142, 17.08.192, 17.08.193, 17.08.194, and 17.72.270 and amended 17.34.010, 17.66.050, and 17.72.150
- What happened next
- Ordinance 2019-19 added permanent cryptocurrency mining and data-center provisions in EWMC Title 17, including Douglas County PUD load verification, Department of Labor and Industries electrical permits, and cryptocurrency-mining definitions
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when City of East Wenatchee votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (14 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.